Works: Installation of Smoke Curtains
Typology: Smoke Curtains
Site: Hamad International Airport
Client: Qatar Airways
Contractor: ADCC JV
Project Duration: 2012
The project included the installation of Smoke Curtains at the New Doha International Aiport, now more commonly known as Hamad International Airport in Qatar. Smoke Barriers and Curtains are used to protect the building's inhabitants from smoke.
​
The project included the installation of 34.000 m2 of Smoke and Fire curtains. It was accomplished in just 4 months (Initial evaluation according to ordinary lead timings was to finish the project in 10 months). Moreover the company had to take extensive safety measures taking into account that technicians had to work at 52m height. Supplier of the Smoke and Fire Curtain was BLE.
![]() |
---|
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |