Works: Installation Of Industrial Doors
Typology: Industrial Doors, from NovoDoors(NovoFirm)
Site: NDIA
Client: Qatar Airways
Contractor: A.D.C.C JV
Project Duration: 2012
The project included the installation of Industrial Doors that was supplied by NovoDoors at the New Doha International Airport, now known as the Hamad International Airport in 2012.
​
In the Cargo Terminal of the New Doha Airport, 150 single-leaf doors, 20 double-leaf doors and 50 automated doors were installed in just 13 working days.
To the Workshop Maintenance Facilities in NDIA, are installed 100 automated grate dimensions doors.
![]() |
---|
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |